At some point during a recent construction project, we found ourselves discussing whether we would need to raise the entrance gate.
There was nothing wrong with the gate. We were simply trying to connect some new sewer pipes to an existing septic tank.
The more we explored how to make the connection work, the more complicated things became.
The pipes needed the right gradient, which meant some sections would have to run above the existing ground level. We might need to backfill parts of the yard, raise the gate and reconsider how rainwater would drain. There was also the existing paving, which we wanted to avoid disturbing.
We discussed rerouting the pipes, removing some paving and using more expensive pipes in certain sections. Each option came with its own complications.
Then I realised something.
Every option assumed that the new pipes had to connect to the existing septic tank.
The plan we had made years earlier
When I built the first house a few years ago, I deliberately made the septic tank and soakaway larger than necessary. I knew I would eventually develop the other half of the plot, so it made sense to allow for that from the beginning.
Why build another septic tank later when the existing one could accommodate the additional buildings?
That was the thinking.
Now we were constructing two flats and a small structure near the entrance gate that included a toilet. Connecting everything to the original system was proving more difficult than I had anticipated.
Yet we kept looking for ways to make it work. We were prepared to change the pipes, the ground levels and even the entrance gate. The original arrangement, however, seemed non-negotiable.
Then I considered another possibility.
What if the new development had its own septic tank?
I discussed it with the plumber and builder. They agreed that it was a viable option. We would have to construct another tank, but we could give the new buildings their own sewer network without disturbing the paving or changing the levels of the yard.
That is what we eventually did.
Looking back, I found it interesting that we had explored so many changes to everything around the septic tank before seriously considering a second one.
It was not some complicated engineering solution we had overlooked. It was a fairly ordinary alternative.
We had simply become so focused on making the original arrangement work that we had not given much thought to doing things differently.
I had done something similar with my cars
The experience reminded me of my first two cars.
My first car was an Audi A4. I loved it, but maintaining it became expensive. The gearbox gave me problems, warning lights kept appearing on the dashboard, and repairs cost a lot of money.
Eventually, I sold it.
But I replaced it with a BMW 320i.
My thinking was that the Audi had been the problem. Surely the BMW would be different.
It wasn’t. I found myself dealing with many of the same issues: expensive servicing, repairs and the costs that came with maintaining that kind of vehicle.
It took me several more years before I bought a Toyota Corolla.
I have written about that experience before, including how some people saw the Corolla as a downgrade.
But I now see another side to that decision.
When I sold the Audi, I changed the car without really reconsidering what I wanted from a car in the first place. I was still choosing within the same idea of what I should be driving.
The Corolla suited my needs much better at that stage of my life. It was reliable, cheaper to maintain and left me with more money for other things.
I did not need to stop driving or give up owning a car. I needed to reconsider the kind of car that made sense for me.
The connection with the construction project is not difficult to see. In both cases, I was looking for a different solution, but within limits I had already set for myself.
The gate is still where it was
The new septic tank has been constructed. The original one continues serving the first building, while the new development has its own sewer network.
The entrance gate is still where it was. So is the paving.
Sometimes I find it amusing that we had reached the point of discussing changes to the gate simply because we were trying to make everything connect to one particular septic tank.
We had spent so much time working out how to make the original arrangement fit that we had nearly missed the option of changing the arrangement itself.
I still think planning ahead was the right thing to do. Making the original tank larger was a sensible decision based on what I knew then.
Just because I made a plan yesterday does not mean everything I do tomorrow has to fit it.